I'm looking for the wire size the terminal can accommodate. I know the recommended is 8 AWG. And you've seen 6 AWG. But, what is the maximum size?
Hi Gang! Thanks for all your comments. I had technicians out to look at it and spoke with several eg4 reps and seems the power is too dirty, they'll i...
@somej Thank you for the pictures! I sent them over to our battery technician. I'll let you know when I get an answer from him. Should be either tomor...
@jp-ouelletteWere you able to get this going?
If the grid isn't connected to the inverter, you can connect the generator to the grid port and enable Micro-Grid mode to prevent it from feeding powe...
Batteries 7-12 are v2 4dip units. The rest are all 6dip v2, v3, or v4.
@eg4eric Here ya go. 8 racks with 6 batteries per rack. The number on each battery corresponds with the number set on that battery's dips. Thank...
8 AWG is what's recommended, but I have seen people use 6 AWGMinute: 12:45
@eg4eric yes, the current open loop LFP charging is a bit of a kludge. I'd be happy to work with the team to define the desired behavior, and/or beta ...
@dtbaker61 I can definitely pass this along to our team. Lead Acid mode wasn’t designed for lithium batteries, which is why it won’t operate exactly a...
@eg4eric , the charge curve and behavior we really want to see for open loop charge control of Lithium batteries is a simple CC-CV curve where:- daily...